Reconstruction work is ongoing at a 4.8-hectare recreation park in Kochkor district, Naryn region of Kyrgyzstan.
According to the Ministry of Construction, the works began in October 2025 and are being financed by the Stabilization Fund.
Under the project, the park will have a 9-meter flagpole, chess and skateboarding areas, an amphitheater, a children’s playground, a cycling path, seating zones with benches, and a parking area. The plan also includes the construction of a public restroom, as well as landscaping and greening of the territory.
To date, installation of the outdoor lighting system and tree planting have already been completed. Asphalt paving and cobblestone works are currently ongoing.